Law: Truman Hoyle

Multi award winning Law Firm
Client: Truman Hoyle
Location: Pitt St, Sydney
Interior Design: BBR
Total Cost: $850,000
Time to Complete: 11 weeks
Total Floor Area: 1300 m2
Special Construction Requirements
  • 2 floor office fitout from an open floor space
  • Large entertaining reception and purpose built library area
  • 3 boardrooms with separate A/C and operable walls
  • Executive offices for partners and workstations for administration
  • Specialist floor finishes
  • Upgrade of lift lobbies to match floor fit out

Project Outline

CBD Projects were engaged as design and construct project managers to upgrade Truman Hoyles offices, to meet with their Award winning corporate image.

The works were all to be completed within the incentive offered by the landlord and within a very tight time frame.

CBD Projects carried out these works by engaging a design company and acting as project managers.

The project was completed in 11 weeks and within the required budget.

The result is a striking new environment that has been enthusiastically received by all Truman Hoyles staff and clients.

Testimonials

"We were impressed from the word 'go'. They saw how we functioned and how we could make improvements. They assured us it would be in on time and on budget. They delivered both those things to us. The whole process was a really happy experience for us to work with both CBD projects and their contractors; we couldn't recommend them more highly."